LYNCHBURG, Va. – Highway work requiring road/lane/structure closures is scheduled, weather permitting. Items in italics contain new/updated information. For up-to-date information, call 511 or visit www.511Virginia.org.

Amherst County:
Route 29 Business – Madison Heights, project to replace median barrier. Lane closures will occur. Use caution. Estimated completion – April 2019.
Route 29 Business at Route 130- Crew will replace back plates on signals.
Route 151 (601- county line) – Shoulder widening & rumble strip project through October 28.
Route 663 – Tree cutting through mid-April will create extended delays. Flaggers will assist motorists.
Surface treatment – Contractor crews will be performing work at various locations. Delays likely.
Various – Crews will work surfaces and respond to customer concerns.

Appomattox County:
Route 460 – Crews will maintain/repair pavement messages.
Plant mix treatment – Beginning April 9, contractor crews will be working at various location. Delays likely.
Various – Crews will work surfaces and respond to customer concerns.

Buckingham County:
Route 20 (Rt. 15, Dillwyn to James River Bridge, Albemarle) – Pavement widening with rumble strips, guardrail replacement/upgrades and paving will take place through summer months. Flaggers and pilot vehicles will control traffic.
Route 633 (Andersonville AHQ) – Crew will work shoulders.
Route 644 & 662 (Andersonville AHQ) – Crew will work on Rural Rustic projects.
Surface treatment – Contractor crews will be performing work at various location. Delays likely.
Various – Crews will cut brush, work surfaces and respond to customer concerns.

Campbell County:
Route 24 @ 646 – Crews will construct roundabout and other improvements. Delays possible.
Route 460 Business – Crews will maintain/repair pavement messages.
Route 696 over Flat Creek (944-709) – Closed for bridge replacement 5/29 thru late July. Detour via Routes 24, 692, and 709 back to 696.
Surface treatment and plant mix- Contractor crews will be performing work on various routes. Delays likely.
Various – Crews will work surfaces and respond to customer concerns.

Charlotte County:
Route 604, Phenix AHQ – Crew will trim trees.
Route 604 and 675, Phenix AHQ: Crews will eradicate pavement markings in advance of surface treatment.
Route 695 over Cub Creek (617 – 727) – Closed thru 5/25 for bridge replacement. Detour via 617, 40 and 727 back to 695.
Routes 807 & 820, Craftons Gate AHQ – Rural Rustic projects underway.
Craftons Gate AHQ – Crew will perform shoulder work on various 4-lane primary routes.
Plant Mix operations – Contractor crews will work at various location. Flaggers and pilot vehicles will assist traffic. Delays likely.
Various – Crews will boom axe, work surfaces and respond to customer concerns.

Cumberland County:
Surface treatment operations: Contractor crews will be performing surface treatment work at various location. Delays likely.
Various – Crew will work surfaces, cut brush, repair drainage and respond to customer concerns.

Halifax County:
Route 58 W over Lawson Creek (501-931) – Lane closure, 11’6” width restriction for bridge work. Est. comp. 5/2018.
Routes 58 & 501, Cluster Springs AHQ – Crew will pick up trash.
Route 619 at Hunting Creek – Bridge weight limit lowered to 16 tons.
Route 670 over Buffalo Creek – Road closed from 639-637 for bridge replacement. Detour via 639 to 638 and 637 back to 670. Estimated completion – June 22.
Plant mix treatment – Beginning April 9, contractor crews will be working at various location. Delays likely.
Bethel AHQ – Crew will boom axe on secondary routes and repair shoulders on primary/secondary routes.
Volens AHQ – Crew will cut right of way.
Various–Crews will work surfaces and respond to customer requests.

Lynchburg:
Route 29/460 (Odd Fellows Rd Int. & Odd Fellows Rd., Phase 1)– Vehicles enter/exit road. Temporary lane closures on 460 & Odd Fellows. Est. comp. 8/3/18. Speed – 45 mph.
Liberty Mtn Dr – Ramp to 460 E closed for roundabout project.
Odd Fellows Road –1-way traffic from Perkins St. to Bradley Dr. to widen road for new interchange. 3-month detour in place for northbound traffic (to Mayflower Dr.).
Odd Fellows and Mayflower intersection –Closed to traffic through June 20. Detours in place.
Odd Fellows to US 29 Expressway – Phase II – Project started. Bridge over RR to be closed for approximately 1 yr – date to be announced.

Nelson County:
Plant mix treatment – Contractor crews will be working on various routes. Delays likely.
Surface treatment – Contractor crews will be working on various routes. Delays likely.
Various – Crews will work surfaces and respond to customer concerns.

Pittsylvania County:
Route 29 Chatham Bypass – Contractor working on northbound median shoulder. Lane closure.
Route 29 North (Route 1080 to 40) – Contractor crew will perform plant mix operations. Alternating lane closures in use. Message boards in place.
Routes 609 & 633, Gretna AHQ – Crew will install crossline pipe.
Routes 644 & 800, Rondo AHQ – Crew will work on Rural Rustic projects.
Routes 686 (two sites) and 802– Temp. lane closures during drilling operations starting April 30.
Route 792, Gretna AHQ – Crew will stabilize bank.
Brosville AHQ – Crew will do ditch work.
Kentuck AHQ – Crew will prune trees.
Rondo AHQ – Crew will clean roadsides.
Various –Crews will boom axe, work surfaces/shoulders and respond to customers.

Prince Edward County:
Route 360 – Crew will perform sign maintenance.
Route 604 – Crew will work on curve straightening project near Route 666.
Route 622- Crews will eradicate pavement markings in advance of surface treatment.
Route 691 – Crew will prepare for Rural Rustic project.
Routes 705 & 748 – Crews will surface treatment.
Plant mix treatment –Contractor crews will be working at various locations. Delays likely.
Various – Crew will cut brush, remove debris, work surfaces and respond to customer concerns.

District-wide activities:
Bridge maintenance – Crews will perform maintenance on bridges.
Guardrail maintenance – Crews will do guardrail maintenance.
Latex applications and line painting – Traffic control will be in use at various locations.
Line painting/pavement marking – Crews will address work orders/requests as able.
Pipe rehabilitation – Crews will rehab/replace pipe at various locations.